Crystal Police Station
Northland Concrete & Masonry played a key role in the construction of the new Crystal Police Station in Crystal, MN. This modern 53,000- square foot facility was built adjacent to City Hall at 4141 Douglas Drive North and was designed to meet the evolving needs of law enforcement and the community. With a project budget of approximately $16 million, construction began in spring 2021 and was completed by summer 2022. The new building includes secure evidence storage, K-9 officer housing, indoor fleet parking, updated detention areas, and new locker rooms. It also involved the demolition and renovation of portions of the original 1965-era City Hall.
As the concrete and masonry subcontractor, NCM was responsible for construction the building’s foundation, cast-in-place concrete walls, structural slabs and masonry elements. Their scope of work included both exterior and interior block walls, site concrete work such as walkways and curbs and any structural concrete needed to support the police facility’s specialized areas.